T.D. Craft Grading completed the civil site development for a new approximately 3,550-square-foot Peoples Bank branch in Pendleton. The compact 0.7-acre site required precise grading and drainage coordination around Clemson Boulevard, Westinghouse Road, an active signalized intersection, existing utilities, and limited working space.
Work Performed
- Removal of existing asphalt, gravel, concrete, and trees
- Billboard, sidewalk, curb, power, and telephone coordination
- Clearing, mass grading, and building-pad preparation
- Parking-lot and drive-aisle preparation
- Fire-access-lane grading
- Light-duty and heavy-duty pavement preparation
- Curb, gutter, sidewalk, and pedestrian-ramp preparation
- ADA parking and accessible-route grading
- Installation of approximately 315 feet of 18-inch storm pipe
- Installation of three curb-inlet catch basins
- Connection to the existing roadside drainage system
- Roof-drain trunk lines and building connections
- Domestic-water service, meter, and backflow installation
- Sanitary-sewer service and cleanout installation
- Erosion control and final stabilization